4/14- ISB Construction Updates

April 14, 2016

Work in Progress: Start forming elevator #2 (south). Grade beam and pile caps along column line #17 between A and G is in progress. Pile caps for elevator #2 are complete. Installing pile caps for Stair #3. Looking forward: Steel erection sequence #1 will begin on…

Read More »

KENT STATE TO HOST ICAM/I2CAM CONFERENCE MAY 16-18

April 12, 2016

17cҳ will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the 17cҳ Hotel and Conference Center.

Read More »

4/7- ISB/Williams Hall Construction Updates

April 7, 2016

Work in Progress: Forming lift 3 on elevator #1. Working on retaining wall progressing south to column line A7. Pile caps and foundations for elevator #2 are complete. Looking forward: Pour lift #3 on elevator #1 on 4/8/2016. Steel delivery and erection begins for…

Read More »

4/7- Smith Hall Renovation Updates

April 7, 2016

Work in Progress: Pulling wire throughout for branch circuits. Installing duct on 1st floor. Complete domestic water rough-in on the 2nd floor. Sanitary piping rough-in has been completed on the 3rd floor. Completing remaining framing throughout. Starting door frame…

Read More »

17cҳ Holds Symposium on “The Neuroscience of the Social Brain” on April 7-8

March 31, 2016

17cҳ’s fourth annual Neuroscience Symposium will cover the latest research findings on “The Neuroscience of The Social Brain” on April 7-8 at the 17cҳ Hotel and Conference Center located in downtown Kent, Ohio.

Read More »

Becoming a Rocket Scientist

March 31, 2016

Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, she’d already earned a dual bachelor’s degree in physics…

Read More »

3/24- Williams Hall/ISB Construction Updates

March 24, 2016

Work in Progress: Working on pile caps and grade beams.  Plan to start column line 17 (Southern most column line) next week. Started working on forming elevator #2 (South). Pouring elevator #1 second lift (North) today. Continuing the installation of the basement…

Read More »

3/24- Smith Hall Renovation Updates

March 24, 2016

Work in Progress: First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun. Room 101 & 104 electrical rough-in is at 90% complete. Machine Shop electric panel installed and completed on Saturday 3/19. Room 223 electrical…

Read More »

3/24- Cunningham Hall Renovation Updates

March 24, 2016

Work in Progress: Steam piping in the 3rd floor east mechanical room is 20% complete. Steam condensate lines for the steam station and AHU#1 are in progress. Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has…

Read More »